TM 5-3805-261-34
FRAME MAINTENANCE.
16-2.
Frame Separation and Connection. (Sheet 9 of 12)
INSTALLATION
7.
Install four lockwashers (39) and
bolts (38, Figure 16-9). Cross
tighten four bolts (38) to 75
ft-lb torque. Tighten one of
four bolts (38) to 75 ft-lb
torque. Tighten one of four
bolts (38) in the upper right
corner of plate (42), then
tighten the next of four bolts
(38) in the lower left corner.
Tighten two remaining of four
bolts (38).
8.
Position pin (50, Figure 16-18).
NOTE
Use two 5/8-11NC x 6 bolts to
keep holes in bottom of pin
in alinement with holes in
plate.
9.
Install two 5/8-11NC x 6 bolts,
through plate (48) and into pin
(50, Figure 16-19).
10.
Install pin (50) completely.
11.
Remove two 5/8-11NC x 6 bolts.
12.
Remove six bolts (46), lock-
washers (47) and plate (48,
Figure 16-20).
13.
Install four lockwashers (45),
bolts (44) and plate (48).
Tighten four bolts (44) to 100
ft-lb torque.