TM 5-3805-261-34
FRAME MAINTENANCE. (cont)
16-2.
Frame Separation and Connection. (Sheet 8 of 12 )
INSTALLATION
1.
Position forklift under rear
frame and remove jack stands.
2.
Apply shop air supply line to
elbow on parking brake actuator
(Figure 16-15) and release
parking brake.
3.
Move rear frame (53) into
position on front frame (54,
Figure 16-16) using forklift.
4.
Using forklift to lift or lower
rear frame (53) and a hydraulic
jack to move it from side to
side, aline bottom pin bore of
rear frame (53) with pin bore of
front frame (54).
NOTE
Install plate to hold spacer
in place.
5.
Install spacer (51), plate (48),
six bolts (46) and lockwashers
(47, Figure 16-17).
NOTE
Using dry ice, lower temperature
of pin to -90 degrees F
to aid in installation.
6.
Install pin (43), plate (42), two
lockwashers (41) and bolts (40,
Figure 16-11).
Go to Sheet 9
16-10
Figure 16-15.
Figure 16-16.
Figure 16-17.
Figure 16-11.