TM 5-3805-293-23-4
0246
ASSEMBLY CONTINUED
000246
11. Install new O-ring (Figure 11, Item 3) and hydraulic fitting (Figure 11, Item 4) on rear valve bank (Figure 11,
Item 7).
12. Install two new O-rings (Figure 11, Item 6) and elbow fittings (Figure 11, Item 5) on rear valve bank (Figure 11,
Item 7).
13. Install three new O-rings (Figure 11, Item 1) and hydraulic fittings (Figure 11, Item 2) on rear valve bank
(Figure 11, Item 7).
Figure 11. Valve Bank Fittings.
0246
END OF TASK
INSTALLATION
000246
WARN I N G
Use extreme caution when handling heavy parts. Provide adequate support and use
assistance during procedure. Ensure any lifting device used is in good condition and of
suitable load capacity. Keep clear of heavy parts supported only by lifting device. Failure to
follow this warning may cause injury or death to personnel.
N OT E
Rear valve bank weighs approximately 160 lb (73 kg).
1. Install lifting link bracket (Figure 12, Item 3), washer (Figure 12, Item 5), and bolt (Figure 12, Item 4) on rear
valve bank (Figure 12, Item 6).
2. Install lifting link bracket (Figure 12, Item 7), washer (Figure 12, Item 9) and nut (Figure 12, Item 8) on rear
valve bank (Figure 12, Item 6).
3. Attach sling and lifting device to rear valve bank (Figure 12, Item 6).