REAR AXLE MAINTENANCE.
5-23.
Final Drive Assembly. (Sheet 5 of 10)
REMOVAL
10.
Install wire from forcing screws
behind housing (39) across planet
carrier (29) to keep planet
carrier (29) from falling.
11.
Position items 16 thru 39 as an
assembly on blocks with planet
carrier (29) facing up. Remove
wire and forcing screws from
housing (39, Figure 5-133).
12.
Remove preformed packing (16) and
gear (17). Discard preformed
packing (16).
Step 13 requires two
mechanics. Weight of planet
carrier is 90 lbs. Failure
to follow this procedure may
cause INJURY. If you are
injured, seek medical aid
immediately.
13.
Using pry bars, carefully remove
items 18 thru 29 as an assembly
turning over and placing on flat
surface.
14.
Remove six bolts (18), three
locks (19), retainers (20) and
shafts (21) from planet carrier
(29, Figure 5-134).
15.
Remove three washers (22 and 23)
and items 24 thru 26 as an
assembly.
16.
Remove three rollers (24 and 25)
from gears (26, Figure 5-135).
WARNING
Figure 5-133.
Figure 5-134.
Figure 5-135.
Go to Sheet 6
5-107