TM 5-3805-261-34
EARTHMOVING
EQUIPMENT
COMPONENTS
MAINTENANCE.
12-2. Blade Assembly. (Sheet 5 of 5)
INSTALLATION
8.
Operate blade sideshift control
and expand cylinder rod to align
with bracket on blade assembly
(3, Figure 12-5).
9.
Install pin (2) and new cotter
pin (1).
10. Operate blade sideshift control
to retract cylinder rod and blade
assembly (3) in place.
11. Remove remaining side of hoist
and sling and second of two
eyebolts from blade assembly (3).
NOTE
Shims are installed between
strip and blade bracket. Add
or remove shim(s) as required
to get a 0.005 to 0.035 inch
gap between blade rail and
strip.
12. Install shim(s) (8), five strips
(7), ten plates (6), 40 washers
(5) and bolts (4, Figure 12-3).
NOTE
Return 13OG Grader to
original equipment condition.
Figure 12-3.
Figure 12-5.
End of Task
12-7