TM 5-3805-261-23-2
MAIN WIRING HARNESS REPLACEMENT - CONTINUED
0286 00
CLEANING AND INSPECTION
Repair main wiring harness, if necessary (WP 0021 00).
INSTALLATION
CAUTION
Do not position main wiring harness against any rough surface. Failure to follow this procedure may cause
chafing.
NOTE
Route main wiring harness exactly as it was removed.
1.
Position main wiring harness (15) on machine.
2.
Connect main wiring harness (15) to EMS panel (6) (WP 0069 00), dimmer switch (7) (WP 0103 00), blade float limit
switch (CCE machine) (8) (WP 0093 00), stop light switch (9) (WP 0108 00), fuse box (11) (WP 0096 00), ether start
temperature switch (4) (WP 0114 00), oil pressure and hourmeter switches (2) (WP 0113 00), air pressure and hourmeter
gauges (3) (WP 0252 00), starting motor (12) (WP 0067 00), alternator (14) (WP 0066 00), and ether start valve (1) (WP
0050 00).
3.
Install new tie straps (13), clamps (10), and clips (5).
4.
Install operator's panel console base (WP 0328 00).
5.
Install left and right side panels on operator's panel console (WP 0193 00).
6.
Install left and right side engine panels (WP 0182 00).
7.
Connect battery cables (WP 0125 00).
END OF WORK PACKAGE
0286 00-3/(-4 Blank)