TM 5-3805-293-23-4
0225
INSTALLATION CONTINUED
30. Install extension pipe (Figure 32, Item 4) on air cleaner housing (Figure 32, Item 10) and tighten clamp
(Figure 32, Item 6)
31. Install clamp (Figure 32, Item 5), nut (Figure 32, Item 9), washer (Figure 32, Item 8), and bolt (Figure 32,
Item 7) on coolant hose (Figure 32, Item 3).
32. Connect hose (Figure 32, Item 3) to coolant tube (Figure 32, Item 1) and install clamp (Figure 32, Item 2).
Figure 32. Air Cleaner Pipe and Coolant Hose.
0225
END OF TASK
FOLLOW-ON TASKS
000225
1. Fill cooling system (WP 0052).
2. Install arctic battery box (if equipped with arctic kit) (WP 0335).
4. Install arctic heater (if equipped with arctic kit) (WP 0342).
END OF TASK
END OF WORK PACKAGE