6. Connect two electrical connectors (Figure 5, Item 1) to fan wiring harness (Figure 5, Item 2).
Figure 5. Connector.
0058
7. Install lower radiator guard (Figure 6, Item 3), four washers (Figure 6, Item 2), and bolts (Figure 6, Item 1) on
machine.
Figure 6. Fan Guard.
0058
END OF TASK
FOLLOW-ON TASKS
00058
1. Connect battery cables (WP 0194).
2. If equipped, install arctic kit battery box (WP 0335).
3. Start engine and check cooling fan for proper operation (TM 5-3805-293-10).
END OF TASK