REAR AXLE MAINTENANCE.
14-18. Differential Carrier. (Sheet 7 of 7)
ASSEMBLY
19. Insert two .250 inch dowels in
splines of shaft (11) 180 degrees
apart. Install socket over shaft
(11) and two dowels (Figure
14-146).
20. Using socket and torque wrench,
check amount of torque needed to
move shaft (11, Figure 14-147)
without preload.
21. Using ratchet, hold shaft (11)
while tightening nut (8) to 6
in-lb torque above the measured
torque without preload.
22. Remove socket from shaft (11).
23. Bend tabs of lock (9) over nut
(8).
24. Install new preformed packings (7
thru 3, Figure 14-148).
25. Install tubes (2 and 1) in
carrier (31).
26. Install differential assembly and
bearing cap. Refer to paragraph
14-17, steps 2 thru 13.
NOTE
Return 130G Grader to
original equipment condition.
Figure 14-147.
Figure 14-146.
Figure 14-148.
End of Task