TM 5-3805-261-34
CHARGING SYSTEM MAINTENANCE. (cont)
4-5.
Alternator (Bosch). (Sheet 11 of 12)
ASSEMBLY
21.
Install items 27 thru 20 as an
assembly on items 54 thru 28 as
an assembly (Figure 4-22) and
aline matchmarks made earlier.
22.
Install four washers (19) and
screws (18) loosely.
23.
Aline stator (28) and rotor (20,
Figure 4-33). Position three
0.001 inch feeler gages.
24.
Tighten four screws (18) to 3 to
4 ft-lb torque. Remove three
feeler gages.
25.
Position one of two field coil
(24) wire assemblies on regulator
(17, Figure 4-21) terminal.
26.
Position remaining field coil
(24) wire assembly and diode
assembly (39) wire assembly on
other regulator (17) terminal.
27.
Install two lockwashers (16) and
screws (15).
28.
Position regulator (17) on rear
of frame (54).
29.
Install two lockwashers (14) and
screws (13).
Go to Sheet 12
4-33
Figure 4-22.
Figure 4-33.
Figure 4-21.