TM 5-3805-261-20
HYDRAULIC SYSTEM MAINTENANCE.
15-16.
Left Blade Lift Check and Relief Valve. (Sheet 2 of 4)
REMOVAL
NOTE
All hose and tube assemblies must be
tagged before disconnecting to aid in
installation. Cap all hose and tube
ends to prevent contamination.
1.
Disconnect hose assemblies (1 and 2,
Figure 15-24).
2.
Disconnect tees (3 and 4).
3.
Remove three bolts (5), washers (6) and
clamp (7).
4.
Remove items 8 thru 16 as an assembly.
5.
Remove elbow (8) and preformed packing
(9,
Figure
15-25).
Discard
preformed
packing (9).
6.
Remove elbow (10) and preformed packing
(11). Discard preformed packing (11).
7.
Remove elbow (12) and preformed packing
(13). Discard preformed packing (13).
8.
Remove elbow (14) and preformed packing
(15). Discard preformed packing (15).
CLEANING
Clean all parts. Refer to Chapter 2.
Figure 15-24.
Figure 15-25.
Go to Sheet 3
15-55