2. Connect transmission harness connector (Figure 8, Item 11) to bulkhead connector (Figure 8, Item 12).
3. Install new lockwasher (Figure 8, Item 9), wiring eyelet (Figure 8, Item 10), and nut (Figure 8, Item 8) on start
relay (Figure 8, Item 13).
4. Install new lockwasher (Figure 8, Item 6), wiring eyelet (Figure 8, Item 5), and nut (Figure 8, Item 7) on start
relay (Figure 8, Item 13).
5. Connect two harness connectors (Figure 8, Item 3) to pigtails (Figure 8, Item 4).
6. Install two harness clips (Figure 8, Item 2), washer (Figure 8, Item 21) and bolt (Figure 8, Item 20) on circuit
breaker box (Figure 8, Item 22).
7. Install two connectors (Figure 8, Item 3) on harness clips (Figure 8, Item 2).
8. Install cable (Figure 8, Item 16) and nut (Figure 8, Item 17) on magnetic switch (Figure 8, Item 18).
9. Install cable (Figure 8, Item 1) and nut (Figure 8, Item 19) on magnetic switch (Figure 8, Item 18).
10. Install tiedown strap (Figure 8, Item 15) on wiring harness (Figure 8, Item 14).
Figure 8. Circuit Breaker Box Wiring Connections.