2
TM 5-3805-293-10
OPERATOR MAINTENANCE
-
SCARIFIER LINK SOCKET INSPECTION
0026
Inspection
INITIAL SETUP
Equipment Condition
Estimated Time to Complete
0
0
0.1 Hr
0
0
0
Personnel Required
0
0
Two
0
INSPECTION
00026
1. Slowly operate scarifier up and down, making very light contact with ground, while having an assistant observe
both scarifier link sockets (Figure 1, Item 1) on each side of machine.
2. Observe sockets (Figure 1, Item 1) for movement without scarifier movement, indicating adjustment is
required.
3. Notify Field Level Maintenance if adjustment is required.
Figure 1. Scarifier Link Sockets.
00026
END OF TASK
END OF WORK PACKAGE
0026-1/(2 blank)