TM 5-3805-261-23-2
COMBINATION VALVE MAINTENANCE - CONTINUED
0323 00
INSTALLATION - CONTINUED
19.
Install new preformed packing (12) and elbow (9).
6
78
5
20.
Install new O-ring (10) and connect hose assembly
(11).
9
21.
Install new preformed packing (5) and elbow (6).
10
22.
Install new O-ring (7) and connect hose assembly (8).
12
11
16
23.
Install new preformed packing (13) and elbow (14).
13
15
14
24.
Install new O-ring (15) and connect hose assembly
397-547
(16).
25.
Install new preformed packing (4) and connector (3).
1
2
3
4
26.
Install new O-ring (2) and connect tube assembly (1).
397-546
27.
Install supplemental steering pressure switch (WP 0087 00).
28.
Fill hydraulic tank to proper level (WP 0216 00).
29.
30.
Turn steering wheel to the left and right while moving the machine slowly forward a few feet.
31.
Repeat step 29 at least five times to bleed air from system.
32.
Stop engine.
33.
Inspect hose assemblies and connections for leaks.
END OF WORK PACKAGE