7.
Install ball (65), spring (64), new preformed packing
63
(63), and plug (62). Tighten plug to 26 lb-ft (35 Nm).
64
8.
Install ball (75), spring (76), new preformed packing
(77), and plug (78). Tighten plug to 25 lb-ft (34 Nm).
65
12
9.
Install choke (73), new preformed packing (72), and
adapter (71). Tighten adapter to 55 lb-ft (75 Nm).
68
10.
Install choke (68), new preformed packing (69), and
69
adapter (70). Tighten adapter to 55 lb-ft (75 Nm).
70
75
76
73
72
77
71
78
397-1541
INSTALLATION
NOTE
Perform steps 1 through 14 to install valve that functions as centershift check valve.
1.
Install check valve (12) to machine with washer (52), and bolt (53).
2.
Install new preformed packing (54) and connector (55) to check valve (12) assembly.
3.
Install new preformed packing (56) and connector (57).
4.
Install new preformed packing (59) and connect hose assembly (61) to connector (55).
5.
Install new preformed packing (58) and connect hose assembly (60) to connector (57).