TM 5-3805-293-23-4
0238
INSTALLATION
000238
N OT E
Install wires and cables as tagged during removal.
1. Install two cables (Figure 2, Item 4) and nuts (Figure 2, Item 9) on main power relay magnetic switch (Figure 2,
Item 5).
2. Install main power relay magnetic switch (Figure 2, Item 5), two washers (Figure 2, Item 7), and nuts (Figure 2,
Item 6) on circuit breaker box (Figure 2, Item 8).
3. Connect connector (Figure 2, Item 1) to wiring harness (Figure 2, Item 2).
4. Install new tiedown strap (Figure 2, Item 3) on wiring harness (Figure 2, Item 2).
0238-3