Clean and inspect all parts IAW Mechanical General Maintenance Instructions (WP 0346).
END OF TASK
ASSEMBLY
00055
1. Install new O-ring (Figure 5, Item 10) and plug (Figure 5, Item 11) on hydraulic oil cooler core (Figure 5,
Item 1).
2. Install two new O-rings (Figure 5, Item 6) and plugs (Figure 5, Item 5) on hydraulic oil cooler core (Figure 5,
Item 1).
N OT E
Install one-way check valve as noted during disassembly.
3. Install new O-ring (Figure 5, Item 7) and check valve (Figure 5, Item 8) on hydraulic oil cooler core (Figure 5,
Item 1).
4. Install new O-ring (Figure 5, Item 12) and fitting (Figure 5, Item 13) on hydraulic oil cooler (Figure 5, Item 1).
N OT E
Install hose as noted during disassembly.
5. Install two new O-rings (Figure 5, Item 9) and hose (Figure 5, Item 2) on hydraulic oil cooler core (Figure 5,
Item 1).
6. Install new O-ring (Figure 5, Item 4) and fitting (Figure 5, Item 3) on hydraulic oil cooler core (Figure 5, Item 1).