14.
Install two new preformed packings (1) and elbows (2
1
and 5) at underside of cab.
3
15.
Install two new preformed packings (3) and connect
4
hose assemblies (4 and 6) to elbows (2 and 5).
5
1
3
6
397-2375
16.
17.
Operate control levers. Move system through at least five full-travel movements to bleed air from system.
18.
Start engine (TM 5-3805-261-10)
19.
Check for leaks.
20.
END OF WORK PACKAGE