TM 5-3805-293-23-4
0183
WIRING HARNESS INSTALLATION CONTINUED
N OT E
Install tiedown straps as noted during removal.
Route wiring harness as noted prior to removal.
If performing this task on machine with seral number prefix CBS, perform steps 10
i
through 12. If performing this task on machine with serial number prefix RMY, perform
steps 7 through 9.
7. Install three clamps (Figure 12, Item 5), washers (Figure 12, Item 6), and bolts (Figure 12, Item 7) on bracket
(Figure 12, Item 4).
8. Connect front worklight wiring harness (Figure 12, Item 2) to front flood lamp assemblies (Figure 12, Item 3).
9. Install new tiedown straps (Figure 12, Item 1) on worklight wiring harness (Figure 12, Item 2).
Figure 12. Front Flood Lamp Connections (Serial Number Prefix RMY).
0183
Change 1