Figure 1. Power Take-Off Line.
BRAKE CONTROL LINES REPLACEMENT

Maintenance Manual For Motorized Road Grader Model 120M - 3
Page Navigation
  907    908    909    910    911  912  913    914    915    916    917  
img
TM 5-3805-293-23-3
0129
INSTALLATION
000129
1. Position power take-off line (Figure 1, Item 2) on machine. Install new O-ring (Figure 1, Item 7) and connect
power take-off line to transmission hydraulic manifold (Figure 1, Item 6).
Install new O-ring (Figure 1, Item 3) and connect power take-off line (Figure 1, Item 2) to flywheel housing
2.
(Figure 1, Item 1).
3. Install two clamps (Figure 1, Item 8), spacer (Figure 1, Item 9), washer (Figure 1, Item 4) and bolt (Figure 1,
Item 5) on power take-off line (Figure 1, Item 2).
END OF TASKS
FOLLOW-ON TASKS
000129
Install engine enclosure (WP 0225).
END OF TASK
END OF WORK PACKAGE