TM 5-3805-261-23-1
SIDESHIFT LINES REPLACEMENT - CONTINUED
0228 00
INSTALLATION - CONTINUED
12.
Install new preformed packings (23 and 25), adapters
(24 and 26), new O-rings (27 and 28), and connect
hose assemblies (29 and 30) to bottom of sideshift
check valve (20)
20
23
24
25 26
30
27 28
29
397-788
.
13.
Position hose assemblies (1 and 4) on machine.
19
17 1
14.
Install new preformed packings (21 and 22), adapters
18
(18 and 19), and new O-rings (17 and 23) and connect
4
hose assemblies (1 and 4) on top of sideshift check
valve (20).
20
23
21
22
397-787
0228 00-10