TM 5-3805-261-23-1
BLADE LIFT LINES, FITTINGS, AND HOSES REPLACEMENT - CONTINUED
0222 00
INSTALLATION - CONTINUED
6.
Install two new preformed packings (74) and tees (62 and 63) to hose assemblies (75 and 76).
7.
Install two new preformed packings (69) and connectors (70 and 78) to left check valve assembly (68).
8.
Position hose assemblies (72 and 77) to machine.
9.
Install two new preformed packings (71) and connect hose assemblies (72 and 77) to connectors (70 and 78).
71
68 69
73
72
70
62 74
75
63
77 73
69 78 71
74
76
397-737
67
10.
Install two new preformed packings (73) and connect
60
hose assemblies (72 and 77) to tees (62 and 63).
11.
Install two new preformed packings (67) and elbows
(60 and 64) to left blade lift check and relief valve
(59).
64
12.
Install two new preformed packings (66) and elbows
66
(58 and 65).
58
67
66
65
397-692